  			                Enter here the start date of the energy measure.
The following applies to the start date of the energy-efficiency measure:
- for measures for which a building permit is required, the date on which the application for a building permit was submitted is considered,
- for measures that do not require a building permit and for which construction documents must be submitted, the date on which the construction documents were submitted is considered,
- for other measures that do not require a permit or notification, the actual start date of construction work on site is considered.